Hitachi Energy and TEİAŞ Commission Türkiye's First Digital Substation Pilot
On 12 May 2026, Hitachi Energy and TEİAŞ announced the commissioning of Türkiye's first digital substation pilot. The scope is one feeder bay.
Relay protection, SCADA, Metering, and Cybersecurity for electrical infrastructure.
On 12 May 2026, Hitachi Energy and TEİAŞ announced the commissioning of Türkiye's first digital substation pilot. The scope is one feeder bay.
UK Power Networks' Constellation project replaces bay-level protection relays with virtualized software on substation computers, using IEC 61850 process bus for local protection and R-GOOSE over 5G for wide area coordination. The first site is operating in Maidstone, Kent, with five more planned across South East England.
Most digital substation projects are single-vendor, single-site proofs of concept. RTE — the operator of France's 2,600-substation transmission grid — decided to do something harder: build a fully digital, multi-vendor PACS from scratch, act as its own system integrator, and scale it across the entire network.
In March 2025, Salt River Project commissioned the first confirmed production deployment of virtualized line differential protection using Routable Sampled Values over MPLS WAN, with ABB SSC600. The WAN-connected virtualized relay proved both faster and more consistent than a conventional microprocessor relay on direct fiber.
Siemens announced SIPROTEC V at DISTRIBUTECH 2026 — a software-defined protection and control system consolidating up to 60 hardware IEDs on a single server. We look at what changes for substation engineers, and what Siemens has not yet disclosed.
On 24 September 2025, NamPower commissioned Sekelduin — a 132/66/33 kV indoor switching station near Swakopmund, Namibia, built by ACTOM as Africa's first fully digital substation with IEC 61850 process bus end-to-end.
CIGRE Study Committee B5 has opened Working Group B5.90, tasked with writing the first dedicated guidelines for commissioning and testing of fully digital protection and automation control systems. The Terms of Reference, published in January 2026, cover FAT, SAT, and operational testing for IEC 61850 process bus architectures.
The UCA IUG conformance registry documents 1,650 test records across three IEC 61850 editions. To read the numbers, you need to know the policy behind them: who sets the transition deadlines, when Edition 2-only testing ended, and why 2023 produced a record spike. This article traces the process.