Taxonomy feed.
UK Power Networks' Constellation project replaces bay-level protection relays with virtualized software on substation computers, using IEC 61850 process bus for local protection and R-GOOSE over 5G for wide area coordination. The first site is operating in Maidstone, Kent, with five more planned across South East England.
Interoperability testing of substation configuration tools (SCT and ICT) has evolved from a supplementary element of the first IOP in 2011 to the central axis of the entire test programme by 2024. At IOP 2019, only 10 out of 159 ICD files (6.28%) passed validation without errors.
Most digital substation projects are single-vendor, single-site proofs of concept. RTE — the operator of France's 2,600-substation transmission grid — decided to do something harder: build a fully digital, multi-vendor PACS from scratch, act as its own system integrator, and scale it across the entire network.
IEC TC57 WG17 has held its kick-off meeting to develop a new document describing how IEC 61850 can be used for monitoring and control of electrical and engineering systems in data centres.
How to use the dumpcap command-line utility for stable long-term network traffic capture — without Wireshark freezes or crashes.
In March 2025, Salt River Project commissioned the first confirmed production deployment of virtualized line differential protection using Routable Sampled Values over MPLS WAN, with ABB SSC600. The WAN-connected virtualized relay proved both faster and more consistent than a conventional microprocessor relay on direct fiber.
Siemens announced SIPROTEC V at DISTRIBUTECH 2026 — a software-defined protection and control system consolidating up to 60 hardware IEDs on a single server. We look at what changes for substation engineers, and what Siemens has not yet disclosed.
On 24 September 2025, NamPower commissioned Sekelduin — a 132/66/33 kV indoor switching station near Swakopmund, Namibia, built by ACTOM as Africa's first fully digital substation with IEC 61850 process bus end-to-end.
IEC TC 57 has approved the New Work Item Proposal for IEC 61850-8-3 with ~95% of national committees voting in favour. The new standard will define a direct mapping of ACSI services onto WebSocket and JSON — a third SCSM alongside MMS and XMPP, designed to extend IEC 61850 beyond the substation.
Top-down IEC 61850 engineering — formalized in TR IEC 61850-90-30:2025 and TR IEC 61850-7-6 (Ed. 2) — moves specification errors from commissioning to the design phase, before a single IED is selected or procured. This article explains the mechanics of the five-step process: what each step produces, what files are exchanged, and why the sequence achieves outcomes the conventional bottom-up approach cannot.
IEC TC 57 Working Group 10 published seven Committee Draft for Vote documents proposing to split the monolithic IEC 61850-7-4 into seven modular parts. The logical node models themselves are not changing — only their structural organisation. Public commenting is open until April 10, 2026.
CIGRE Study Committee B5 has opened Working Group B5.90, tasked with writing the first dedicated guidelines for commissioning and testing of fully digital protection and automation control systems. The Terms of Reference, published in January 2026, cover FAT, SAT, and operational testing for IEC 61850 process bus architectures.
The UCA IUG conformance registry documents 1,650 test records across three IEC 61850 editions. To read the numbers, you need to know the policy behind them: who sets the transition deadlines, when Edition 2-only testing ended, and why 2023 produced a record spike. This article traces the process.