Most digital substation projects are single-vendor, single-site proofs of concept. RTE — the operator of France's 2,600-substation transmission grid — decided to do something harder: build a fully digital, multi-vendor PACS from scratch, act as its own system integrator, and scale it across the entire network.
IEC TC 57 Working Group 10 published seven Committee Draft for Vote documents proposing to split the monolithic IEC 61850-7-4 into seven modular parts. The logical node models themselves are not changing — only their structural organisation. Public commenting is open until April 10, 2026.
The UCA IUG conformance registry documents 1,650 test records across three IEC 61850 editions. To read the numbers, you need to know the policy behind them: who sets the transition deadlines, when Edition 2-only testing ended, and why 2023 produced a record spike. This article traces the process.